Consent Agenda
123/2026
Approve Change Order #2 for IFB #029-46 Construction of the Realignment of White Sulphur Road - Phase II
Board Of Commissioners Voting Meeting on 2026-03-26 at 06:00 PM

Approve Change Order #2 to IFB #029-46 Construction of the Realignment of White Sulphur Road - Phase II for Public Works & Utilities to add a modular Gravix wall and additional water main fittings to Wilson Construction Management, LLC of Norcross, GA, in the amount of $133,052.00.